Affinely adjustable robust model for multiperiod production planning under uncertainty

Byung Soo Kim, Byung Do Chung

Research output: Contribution to journalArticle

5 Citations (Scopus)

Abstract

Demand forecasting is an important factor in production planning, but future demand is not easy to forecast in practice. We consider a multiperiod, multiproduct production planning problem under demand uncertainty with constrains for raw materials, manufacturing capacity, and inventory. Under the assumption that probability distribution of demand is not available, two types of robust optimization models are proposed. First, a robust counterpart is developed to determine the here-And-now decision. Next, an affinely adjustable robust counterpart is developed to determine the wait-And-see decisions by approximating a robust solution with a linear decision rule. The robust models find an optimal solution that is always feasible and less sensitive against all realized demand within a given uncertainty set, in order to minimize production, procurement, inventory, and lost sales costs even in the worst case. Numerical studies demonstrated that, without knowing probability distribution of future demand, the affinely adjustable robust counterpart approach could outperform the robust counterpart and deterministic model in terms of the average cost, the standard deviation of the realized cost, and the worst-case scenario cost. The proposed method is much better than the others, especially when penalty cost due to lost sales is high and unknown demand is left skewed.

Original languageEnglish
Article number7903707
Pages (from-to)505-514
Number of pages10
JournalIEEE Transactions on Engineering Management
Volume64
Issue number4
DOIs
Publication statusPublished - 2017 Nov 1

Fingerprint

Planning
Costs
Probability distributions
Sales
Raw materials
Uncertainty
Production planning
Probability distribution
Lost sales

All Science Journal Classification (ASJC) codes

  • Strategy and Management
  • Electrical and Electronic Engineering

Cite this

@article{50df048304b64295bbc11ebb77ba851a,
title = "Affinely adjustable robust model for multiperiod production planning under uncertainty",
abstract = "Demand forecasting is an important factor in production planning, but future demand is not easy to forecast in practice. We consider a multiperiod, multiproduct production planning problem under demand uncertainty with constrains for raw materials, manufacturing capacity, and inventory. Under the assumption that probability distribution of demand is not available, two types of robust optimization models are proposed. First, a robust counterpart is developed to determine the here-And-now decision. Next, an affinely adjustable robust counterpart is developed to determine the wait-And-see decisions by approximating a robust solution with a linear decision rule. The robust models find an optimal solution that is always feasible and less sensitive against all realized demand within a given uncertainty set, in order to minimize production, procurement, inventory, and lost sales costs even in the worst case. Numerical studies demonstrated that, without knowing probability distribution of future demand, the affinely adjustable robust counterpart approach could outperform the robust counterpart and deterministic model in terms of the average cost, the standard deviation of the realized cost, and the worst-case scenario cost. The proposed method is much better than the others, especially when penalty cost due to lost sales is high and unknown demand is left skewed.",
author = "Kim, {Byung Soo} and Chung, {Byung Do}",
year = "2017",
month = "11",
day = "1",
doi = "10.1109/TEM.2017.2691404",
language = "English",
volume = "64",
pages = "505--514",
journal = "IEEE Transactions on Engineering Management",
issn = "0018-9391",
publisher = "Institute of Electrical and Electronics Engineers Inc.",
number = "4",

}

Affinely adjustable robust model for multiperiod production planning under uncertainty. / Kim, Byung Soo; Chung, Byung Do.

In: IEEE Transactions on Engineering Management, Vol. 64, No. 4, 7903707, 01.11.2017, p. 505-514.

Research output: Contribution to journalArticle

TY - JOUR

T1 - Affinely adjustable robust model for multiperiod production planning under uncertainty

AU - Kim, Byung Soo

AU - Chung, Byung Do

PY - 2017/11/1

Y1 - 2017/11/1

N2 - Demand forecasting is an important factor in production planning, but future demand is not easy to forecast in practice. We consider a multiperiod, multiproduct production planning problem under demand uncertainty with constrains for raw materials, manufacturing capacity, and inventory. Under the assumption that probability distribution of demand is not available, two types of robust optimization models are proposed. First, a robust counterpart is developed to determine the here-And-now decision. Next, an affinely adjustable robust counterpart is developed to determine the wait-And-see decisions by approximating a robust solution with a linear decision rule. The robust models find an optimal solution that is always feasible and less sensitive against all realized demand within a given uncertainty set, in order to minimize production, procurement, inventory, and lost sales costs even in the worst case. Numerical studies demonstrated that, without knowing probability distribution of future demand, the affinely adjustable robust counterpart approach could outperform the robust counterpart and deterministic model in terms of the average cost, the standard deviation of the realized cost, and the worst-case scenario cost. The proposed method is much better than the others, especially when penalty cost due to lost sales is high and unknown demand is left skewed.

AB - Demand forecasting is an important factor in production planning, but future demand is not easy to forecast in practice. We consider a multiperiod, multiproduct production planning problem under demand uncertainty with constrains for raw materials, manufacturing capacity, and inventory. Under the assumption that probability distribution of demand is not available, two types of robust optimization models are proposed. First, a robust counterpart is developed to determine the here-And-now decision. Next, an affinely adjustable robust counterpart is developed to determine the wait-And-see decisions by approximating a robust solution with a linear decision rule. The robust models find an optimal solution that is always feasible and less sensitive against all realized demand within a given uncertainty set, in order to minimize production, procurement, inventory, and lost sales costs even in the worst case. Numerical studies demonstrated that, without knowing probability distribution of future demand, the affinely adjustable robust counterpart approach could outperform the robust counterpart and deterministic model in terms of the average cost, the standard deviation of the realized cost, and the worst-case scenario cost. The proposed method is much better than the others, especially when penalty cost due to lost sales is high and unknown demand is left skewed.

UR - http://www.scopus.com/inward/record.url?scp=85018626864&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=85018626864&partnerID=8YFLogxK

U2 - 10.1109/TEM.2017.2691404

DO - 10.1109/TEM.2017.2691404

M3 - Article

AN - SCOPUS:85018626864

VL - 64

SP - 505

EP - 514

JO - IEEE Transactions on Engineering Management

JF - IEEE Transactions on Engineering Management

SN - 0018-9391

IS - 4

M1 - 7903707

ER -