Formulation of a pull production system for optimal inventory control of temporary rebar assembly plants

Keon Soon Im, Seung Heon Han, Bonsang Koo, Do Young Jung

Research output: Contribution to journalArticle

5 Citations (Scopus)

Abstract

Temporary fabrication plants such as rebar assembly and precast segment shops are increasingly used in large scale construction projects to provide a construction site of its material needs. A plant needs to be operated in such a way that it is flexible enough to adapt to changing project demands while minimizing inventories. Meeting such needs requires careful control of the level of raw materials and assembly products fabricated in the plant, the two main types of inventories. However, in practice the ordering of raw materials and assembly times are ad hoc, leading to excess inventories and added costs to the project. This paper presents a methodology for effective, efficient, and economic control of inventory levels in temporary rebar assembly plants. Ordering processes are formalized to convert existing approaches into a pull production system. Given this transformation, a methodology is presented that employs Monte Carlo simulation and optimization techniques to identify inventory levels that minimize inventory costs while simulating variability in demand, procurement lead times, and production capacity. A retrospective case on a rebar assembly plant shows that the same amount of work can be performed with significantly less inventory levels when applying the proposed production methodology. It also provides evidence that the cost savings from inventory costs outweigh any additional holding or delivery costs associated with a pull production system.

Original languageEnglish
Pages (from-to)1444-1458
Number of pages15
JournalCanadian Journal of Civil Engineering
Volume36
Issue number9
DOIs
Publication statusPublished - 2009 Oct 27

Fingerprint

Inventory control
production system
Costs
Raw materials
cost
methodology
Fabrication
Economics
savings
economics

All Science Journal Classification (ASJC) codes

  • Civil and Structural Engineering
  • Environmental Science(all)

Cite this

@article{fda1006fca4c4e519a4def0930f27009,
title = "Formulation of a pull production system for optimal inventory control of temporary rebar assembly plants",
abstract = "Temporary fabrication plants such as rebar assembly and precast segment shops are increasingly used in large scale construction projects to provide a construction site of its material needs. A plant needs to be operated in such a way that it is flexible enough to adapt to changing project demands while minimizing inventories. Meeting such needs requires careful control of the level of raw materials and assembly products fabricated in the plant, the two main types of inventories. However, in practice the ordering of raw materials and assembly times are ad hoc, leading to excess inventories and added costs to the project. This paper presents a methodology for effective, efficient, and economic control of inventory levels in temporary rebar assembly plants. Ordering processes are formalized to convert existing approaches into a pull production system. Given this transformation, a methodology is presented that employs Monte Carlo simulation and optimization techniques to identify inventory levels that minimize inventory costs while simulating variability in demand, procurement lead times, and production capacity. A retrospective case on a rebar assembly plant shows that the same amount of work can be performed with significantly less inventory levels when applying the proposed production methodology. It also provides evidence that the cost savings from inventory costs outweigh any additional holding or delivery costs associated with a pull production system.",
author = "Im, {Keon Soon} and Han, {Seung Heon} and Bonsang Koo and Jung, {Do Young}",
year = "2009",
month = "10",
day = "27",
doi = "10.1139/L09-072",
language = "English",
volume = "36",
pages = "1444--1458",
journal = "Canadian Journal of Civil Engineering",
issn = "0315-1468",
publisher = "National Research Council of Canada",
number = "9",

}

Formulation of a pull production system for optimal inventory control of temporary rebar assembly plants. / Im, Keon Soon; Han, Seung Heon; Koo, Bonsang; Jung, Do Young.

In: Canadian Journal of Civil Engineering, Vol. 36, No. 9, 27.10.2009, p. 1444-1458.

Research output: Contribution to journalArticle

TY - JOUR

T1 - Formulation of a pull production system for optimal inventory control of temporary rebar assembly plants

AU - Im, Keon Soon

AU - Han, Seung Heon

AU - Koo, Bonsang

AU - Jung, Do Young

PY - 2009/10/27

Y1 - 2009/10/27

N2 - Temporary fabrication plants such as rebar assembly and precast segment shops are increasingly used in large scale construction projects to provide a construction site of its material needs. A plant needs to be operated in such a way that it is flexible enough to adapt to changing project demands while minimizing inventories. Meeting such needs requires careful control of the level of raw materials and assembly products fabricated in the plant, the two main types of inventories. However, in practice the ordering of raw materials and assembly times are ad hoc, leading to excess inventories and added costs to the project. This paper presents a methodology for effective, efficient, and economic control of inventory levels in temporary rebar assembly plants. Ordering processes are formalized to convert existing approaches into a pull production system. Given this transformation, a methodology is presented that employs Monte Carlo simulation and optimization techniques to identify inventory levels that minimize inventory costs while simulating variability in demand, procurement lead times, and production capacity. A retrospective case on a rebar assembly plant shows that the same amount of work can be performed with significantly less inventory levels when applying the proposed production methodology. It also provides evidence that the cost savings from inventory costs outweigh any additional holding or delivery costs associated with a pull production system.

AB - Temporary fabrication plants such as rebar assembly and precast segment shops are increasingly used in large scale construction projects to provide a construction site of its material needs. A plant needs to be operated in such a way that it is flexible enough to adapt to changing project demands while minimizing inventories. Meeting such needs requires careful control of the level of raw materials and assembly products fabricated in the plant, the two main types of inventories. However, in practice the ordering of raw materials and assembly times are ad hoc, leading to excess inventories and added costs to the project. This paper presents a methodology for effective, efficient, and economic control of inventory levels in temporary rebar assembly plants. Ordering processes are formalized to convert existing approaches into a pull production system. Given this transformation, a methodology is presented that employs Monte Carlo simulation and optimization techniques to identify inventory levels that minimize inventory costs while simulating variability in demand, procurement lead times, and production capacity. A retrospective case on a rebar assembly plant shows that the same amount of work can be performed with significantly less inventory levels when applying the proposed production methodology. It also provides evidence that the cost savings from inventory costs outweigh any additional holding or delivery costs associated with a pull production system.

UR - http://www.scopus.com/inward/record.url?scp=70350223481&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=70350223481&partnerID=8YFLogxK

U2 - 10.1139/L09-072

DO - 10.1139/L09-072

M3 - Article

AN - SCOPUS:70350223481

VL - 36

SP - 1444

EP - 1458

JO - Canadian Journal of Civil Engineering

JF - Canadian Journal of Civil Engineering

SN - 0315-1468

IS - 9

ER -